Task # 2.a.: Performing Float Switch Testing on Vessels with Drain Valve Configurations

ACTION

COMMENT

39.

Repeat this Maintenance Procedure for each float switch with a drain valve con- figuration, starting with Task # 1 “Prepar- ing for Float Switch Testing.” If this is the last float switch to be tested today, cleanup your work area. Secure your equipment and prepare to document your work. Continue to Task # 3 “Documenting Float Switch Testing.”

See Task # 1 of this Maintenance Procedure.

40.

See Task # 3 of this Maintenance Procedure.

RETA TECHNICAL REPORT PAGE 13